A pre-application assessment for demand connections at any GB Grid Supply Point — built on NESO open data, TMO4+ reform criteria and the CP30 Action Plan.
Four things every developer needs before committing to a connection application.
All 250+ GB Grid Supply Points on an interactive map with live headroom and capacity overlays.
An instant Gate 2 readiness check against the current Connections Reform criteria.
Proximity analysis and satellite links for every Grid Supply Point and site location.
A professional pre-application report you can download as .docx or print to PDF instantly.
From postcode to a downloadable pre-application report in under ten minutes.
Enter your organisation, site postcode, requested capacity in MW and target energisation date. Connection type is optional — skip it and we assess generally.
Firm or non-firm? Rigid or phased demand? Flexibility appetite? These four questions shape the scope of your assessment and often shift your connection date by years.
Pick your Grid Supply Point from the map and generate a full pre-application report with headroom analysis, indicative timelines and next steps.
Knowing what comes next — and what the network operator will ask — makes that first conversation far shorter. This tool sits at the very front of the process.
Understand the capacity picture at your location, what a firm connection costs you in time, and which questions the operator will ask. No fee, no commitment, no queue position.
An informal request to your DNO or NESO for an indicative cost and connection date. Non-binding, but the first time your project is seen by the operator.
A full application with site, capacity, technology and programme detail. This is what establishes your position in the connections queue.
Under Connections Reform, projects are gated on land rights and readiness. Gate 2 carries a firm date; Gate 1 holds an indicative one until evidence is supplied.
A formal offer setting out cost, date, and any reinforcement or curtailment terms. Time-limited — you must accept within the offer window.
Design, consents, reinforcement works and commissioning, through to first power at your agreed capacity — staged if you took a ramped connection.
Two public registers, pulled live, and joined to your site location by postcode.
The Transmission Entry Capacity register lists every project holding a contract for entry capacity on the national transmission system — connected, contracted and queued.
Every DNO publishes an ECR of generation, storage and flexible demand at 50kW and above, connected or accepted to connect, in a format standardised through DCUSA and the ENA.
Your postcode is geocoded, matched to the nearest point of connection, and plotted on a GB-wide open map with satellite imagery and Google Earth links for site inspection.
Your connection is delivered by one of these bodies — the system operator, the regulator, three transmission owners and six distribution groups covering 14 licence areas.
Three onshore transmission owners run the high-voltage backbone: National Grid across England and Wales, SP Energy Networks in southern Scotland and SSEN Transmission in the north. NESO is system operator for England, Scotland and Wales.
Six DNO groups own and operate the wires across 14 licence areas in Great Britain. Your DNO is fixed by your site postcode, not by your electricity supplier — and it is the body you apply to for a distribution connection.
Network maps and operator names shown for reference only. This is an independent pre-application assessment tool and is not endorsed by, affiliated with, or issued on behalf of any network operator, NESO, Ofgem, the ENA or DESNZ.
Not sure which DNO covers your site? The ENA's official lookup finds your network operator from your postcode — the same body you will apply to, and the one you call on 105 in a power cut.
Find My Network Operator →This is one of the most consequential decisions in your connection journey. A firm connection gives you a guaranteed, continuous supply of power up to your contracted capacity — at all times, regardless of conditions on the network.
A firm connection means the DNO or NESO guarantees to supply (or accept) your contracted capacity at any point in time. The network is designed and reinforced specifically to accommodate your load. You have a legal right to draw your full contracted capacity 24/7.
Benefits: Security of supply · Operational certainty · Suitable for critical loads (hospitals, data centres, manufacturing) · Bankable for project finance · No risk of curtailment
Risks / Costs: Typically requires more reinforcement, hence longer wait times and higher connection costs. Queue position is more competitive. You pay for reinforcement even if your load is intermittent.
A non-firm (interruptible) connection means you can draw power most of the time, but the DNO/NESO retains the right to curtail or interrupt your supply during periods of system stress, constraint, or emergency. You will have a lower capacity "firm" element and an "interruptible" element subject to curtailment.
Benefits: Significantly faster connection date — often 2 to 5 years earlier than a firm equivalent · Lower upfront connection costs · Smaller reinforcement obligation · Useful where load can tolerate interruption (e.g. flexible manufacturing, some EV charging depots, certain battery charging activities)
Risks: No guarantee of full supply · Must have curtailment management capability · May not be bankable for all lenders · Not suitable for continuous critical loads
| Factor | Firm | Non-Firm |
|---|---|---|
| Guaranteed supply | Yes – always | No – may be curtailed |
| Connection date | Longer wait | Up to 5 yrs earlier |
| Cost | Higher | Lower |
| Suitable for data centres | Yes | Usually not |
| Suitable for EV fleet charging | Yes | Often yes |
| Project finance bankability | Generally yes | Case by case |
Many developers assume they need their full capacity from day one. In practice, most large demand projects ramp up gradually — and taking a ramped or phased connection approach can dramatically improve your connection date.
A ramped connection (also called a phased or stepped connection) is where you connect at a lower initial capacity and increase to your full contracted capacity in agreed stages over time. For example, connecting at 15MW initially, stepping to 30MW in 2028, and reaching full 50MW in 2030.
The DNO designs the connection so each phase can be delivered in alignment with existing network capacity and planned reinforcement works. You only pay for and draw each tranche as it becomes available.
Network headroom is not uniform over time. A substation that cannot accommodate 50MW today may have 15MW of spare capacity right now — from a departed customer, a demand reduction, or a planned flexibility action. A ramped connection lets you:
For data centres: Phase 1 shell and core at 15MW, scale rack density to 30MW by Phase 2, full campus at 50MW by Phase 3 — fully aligned with real-world buildout schedules.
For EV hubs: Open the depot at 8MW rapid chargers, add ultra-rapid bays as the tranche increases. Cash flow matches connection.
| Factor | Full Capacity from Day 1 | Ramped / Phased |
|---|---|---|
| Time to first connection | Longer – full reinforcement needed | Much faster – existing headroom used first |
| Initial connection cost | Higher – all works upfront | Lower – phased investment |
| Operational start | Delayed | Earlier – start earning sooner |
| Complexity | Simpler agreement | More complex offer terms |
| Suitable if load grows over time | Wastes early contracted capacity | Perfectly aligned |
Under the TMO4+ Connections Reform (live since 10 June 2025), the connections process operates through a gated system. Understanding what is expected at each gate is essential before you apply.
What you get: An indicative connection date and location only. No firm date, no reinforcement works confirmed, no securities required at this stage.
What you must provide: A valid application with competency information, project type, location, and requested capacity. For embedded demand projects, you apply directly to your DNO (e.g. SSE Distribution). For transmission-direct connections, you apply to NESO.
What happens next: Your project is placed in the indicative queue. You can advance to Gate 2 when ready. Gate 1 does not entitle you to a confirmed connection date or the start of network studies.
To receive a firm Gate 2 connection offer, you must demonstrate two things:
1. Readiness Criteria — You must prove you are genuinely ready to build. You can satisfy this via:
2. Strategic Alignment Criteria — Your project type must fall within the permitted zonal capacity allocations set by the CP30 Action Plan. Technology and regional capacity caps apply. For demand projects, you must demonstrate your demand is real, located where it is needed, and consistent with strategic plans.
After accepting your Gate 2 offer, you must meet a structured set of 7 Queue Management Milestones on a legally binding schedule. These include:
Failure to meet milestones on time can result in termination of your connection agreement. A 60-day rectification period applies before termination. The Progression Commitment Fee (under proposal CMP448) will add financial consequences to abandonment.
Large embedded demand or generation projects that connect to the distribution network can still impact the transmission system. NESO carries out a Transmission Impact Assessment (TIA) — or Transmission Entry Assessment (TEA) for demand — for projects above certain size thresholds.
If your project exceeds the threshold, your DNO (e.g. SSE Distribution) must obtain transmission consent from NESO before your distribution connection offer becomes firm. This means TMO4+ Gate 2 criteria apply to your project even though you connect at distribution voltage.
If you are below the threshold, you are out of scope of TMO4+ and follow a standard DNO-only process without gated windows — typically faster and simpler.